Moving in before finishing.
• 10’ ceiling (lighting will be more even, room for hoist - see next item - smooth wall & ceiling surfaces.Folks have any "wish I had done this earlier" for their shop?
My question is situated in wanting to know if there's anything I should do as part of my initial build that might prove difficult later on? Folks gave good responses above already that I've noted down.
I always recommend Epoxy/Urethane/Polyamine floor topping, not a coating: toppings are 1/4” - 3/8” thick and will stand up to significantly more abuse than a coating (which is basically paint). Industrial need to be installed by a certified installer, who will also provide requirements for the concrete floor, vapor barrier and curing time (look what happened in DC recently when proper procedures weren’t followed).One of these items I'm now leaning towards is the acid etched epoxy finish that would be a pain to do later once I fill up the space. If I need to do indoor welding or worried about messing up the floor I can just lay down some cement board to make a "dirty" corner".
But I should be safe if I don't let invisible vandals with boxcutters in, right?Industrial need to be installed by a certified installer, who will also provide requirements for the concrete floor, vapor barrier and curing time (look what happened in DC recently when proper procedures weren’t followed).
Understand from previous posts the limited lot space. From experience moving machines in and out of difficult locations with previous shops, suggest a poured concrete sidewalk/approach from street. Hopefully enough space for a small forklift and/or pallet jack and load. Concrete should make for easier rolling. Is there a fence on that side between your place and neighbour?
I have interlock at front and side of house and will continue this to the workshop overhead doors to form a continuous path. Only got 36" clear but can get just under 48" if I temporarily remove the window wells. The clear path is on my mind because I would need a forklift/pallet jack to move the lathes/mills from the front garage into the back once it's all done.
I'm planning on the 6ft pad outside the overhead doors as well. While it would be good to have this concrete using the same subs, I may have to go interlock because of "soft landscape" by-laws. TBD and will see what I can get away with!
Fence on all three side at property line.
When your grinder/saw/ etc trips a breaker and you end up in the dark with your half finished project around you, that is when you wished the lights were on their own breaker.
Ceiling is unfinished, same with the cupboards and airlines. I always say I won't but I always do this. For good reason of course.Can you elaborate?
I would suggest a dedicated circuit for any mag chuck on a surface grinder. If there is something else on that circuit that could pop the breaker things can get ugly quickly. I also won't grind when it is windy out.Things that seem really logical to me but seem to have escaped many of the electricians that wired the houses I bought, is don't have the lights share any circuits with outlets, especially for a garage & workshop - this is a safety thing.
When your grinder/saw/ etc trips a breaker and you end up in the dark with your half finished project around you, that is when you wished the lights were on their own breaker.
Anchor points in the floor can be handy for moving stuff around.Understand from previous posts the limited lot space. From experience moving machines in and out of difficult locations with previous shops, suggest a poured concrete sidewalk/approach from street. Hopefully enough space for a small forklift and/or pallet jack and load. Concrete should make for easier rolling. Is there a fence on that side between your place and neighbour?
Anchor points in the floor can be handy for moving stuff around.
Having slipped on polished concrete in an office building I would not have polished concrete anywhere.Thoughts on polished concrete over epoxy? I get the slippery concern but this will be a pretty clean space.
I have interlock at front and side of house and will continue this to the workshop overhead doors to form a continuous path. Only got 36" clear but can get just under 48" if I temporarily remove the window wells. The clear path is on my mind because I would need a forklift/pallet jack to move the lathes/mills from the front garage into the back once it's all done.
I'm planning on the 6ft pad outside the overhead doors as well. While it would be good to have this concrete using the same subs, I may have to go interlock because of "soft landscape" by-laws. TBD and will see what I can get away with!
Fence on all three side at property line.
I can appreciate your idea of future proofing.Something I’m considering is doing electrical in conduit, over the drywall so I can easily make changes later.