• Scam Alert. Members are reminded to NOT send money to buy anything. Don't buy things remote and have it shipped - go get it yourself, pay in person, and take your equipment with you. Scammers have burned people on this forum. Urgency, secrecy, excuses, selling for friend, newish members, FUD, are RED FLAGS. A video conference call is not adequate assurance. Face to face interactions are required. Please report suspicions to the forum admins. Stay Safe - anyone can get scammed.

Show us your shops!

No columns in middle! It is currently 4 LVLs bolted together spanning the entire 31' with timber posts on both ends. Joists in between.

I did just inquiry about an I-beam yesterday and the building came back with a 1500-2000$ premium over LVLs for a W10-26. So I'm sticking with wood mainly because of costs but also would be easier if I needed to bold anything into the beam for other uses. I'm a little nervous about all these incremental costs that seem fine on its own but they all add up quickly.

A smaller beam doesn't necessarily need posts in the middle of your shop to support it. It could hang on rods from the roof trusses with relatively modest roof strength improvements. Depending on the span, they might be needed anyway.
 
A smaller beam doesn't necessarily need posts in the middle of your shop to support it. It could hang on rods from the roof trusses with relatively modest roof strength improvements. Depending on the span, they might be needed anyway.

I was worried about overloading the mezzanine and stressing the roof but this anxiety isn't informed by anything since I am no engineer and with limited practice of loading and rigging. I asked for clearance below so the proposed solution by the engineer and builder is closer to a gantry design as shown above with 4x LVLs.

Now I am thinking of one or two additional beams on the same plane. I can have a hoist towards the back and even build out another small shelf to store above. Looking for thoughts and suggestions from folks here!
 
Last edited:
I was worried about overloading the mezzanine and stressing the roof

One way to think about it is that all roofs in Canada have to be designed and built to handle the design snow load for that area. With the right designs to spread the loads the same way that snowloads are carried, supports for your mezzanine can be carried just like a bigger snow load would be.
 
One way to think about it is that all roofs in Canada have to be designed and built to handle the design snow load for that area. With the right designs to spread the loads the same way that snowloads are carried, supports for your mezzanine can be carried just like a bigger snow load would be.

Oh right! I'll talk the builder to see if a design to strengthen the roof without much much material or labour could be added increase the load capacity for the mezzanine with a few rod ties. But if all that gets close to the cost of a metal beam I may have to forgo... will explore it!
 
One way to think about it is that all roofs in Canada have to be designed and built to handle the design snow load for that area. With the right designs to spread the loads the same way that snowloads are carried, supports for your mezzanine can be carried just like a bigger snow load would be.
Except that snow load is assumed to be uniform (other than at drifting portions of the roof), wheras the hanging loads for the mezzanine (and/or hoist) would be point loads at the connections.
 